— Project Summary

Queue ID
TVA-416
Capacity
780 MW
Technology
Gas
Status
active
Location
Colbert, AL
Region
Southeast
Developer
IA Status
IA Executed

BetaActiveGasTVALBNL

780 MW generation in Colbert, AL · In queue since February 2020 · Proposed COD October 2022

780 MW

Capacity

1

Components

Gas

6y 1m

In Queue

IA Executed

IA Status

COD target: 2022

Interconnection Timeline

Total Duration

2y 8m

Schedule

42 months past proposed COD

Construction75%
Queue EntryFeb 10, 2020

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 24–48 months

Commercial Operation

Proposed COD: 2022-10-01

Project Details

State

AL

County

Colbert

Region

Southeast

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Point of Interconnection

Colbert Fossil Plant 161-kV Station

Data Source

LBNL

No news available for this project.