BetaActiveSolarTVALBNL
193 MW generation in Lawrence, AL · In queue since November 2019 · Proposed COD May 2027
193 MW
Capacity
1
Components
Solar
6y 4m
In Queue
IA Executed
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
7y 6m
Construction75%
Queue EntryNov 18, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2027-05-28
Project Details
State
AL
County
Lawrence
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
CR BRK 242 - Mountain Home 161-kV TL
Data Source
LBNL