69 MW generation in Simpson, KY · In queue since August 2019 · Proposed COD June 2025
69 MW
Capacity
1
Components
Solar
6y 7m
In Queue
IA Executed
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
5y 10m
Schedule
9 months past proposed COD
Construction75%
Queue EntryAug 1, 2019
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2025-06-25
Project Details
State
KY
County
Simpson
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
Portland - Franklin 161-kV TL
Data Source
LBNL