— Project Summary

Queue ID
TVA-379
Capacity
50 MW
Technology
Battery
Status
active
Location
Lowndes, MS
Region
Southeast
Developer
IA Status
IA Executed

BetaActiveBatteryTVALBNL

50 MW storage in Lowndes, MS · In queue since June 2019 · Proposed COD September 2024

50 MW

Capacity

1

Components

Battery

6y 9m

In Queue

IA Executed

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

5y 3m

Schedule

18 months past proposed COD

Construction75%
Queue EntryJun 11, 2019

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 6–18 months

Commercial Operation

Proposed COD: 2024-09-24

Project Details

State

MS

County

Lowndes

Region

Southeast

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Point of Interconnection

Artesia 161-kV Substation (future)

Data Source

LBNL

No news available for this project.