— Project Summary

Queue ID
TVA-332
Capacity
23 MW
Technology
Gas
Status
active
Location
Shelby, TN
Region
Southeast
Developer
IA Status
IA Executed

BetaActiveGasTVALBNL

23 MW generation in Shelby, TN · In queue since October 2017 · Proposed COD February 2018

23 MW

Capacity

1

Components

Gas

8y 5m

In Queue

IA Executed

IA Status

COD target: 2018

Interconnection Timeline

Total Duration

4 months

Schedule

98 months past proposed COD

Construction75%
Queue EntryOct 18, 2017

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 24–48 months

Commercial Operation

Proposed COD: 2018-02-28

Project Details

State

TN

County

Shelby

Region

Southeast

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Point of Interconnection

Allen 161-kV Substation

Data Source

LBNL

No news available for this project.