— Project Summary

Queue ID
TVA-321
Capacity
11 MW
Technology
Hydro
Status
active
Location
Marion, TN
Region
Southeast
Developer
IA Status
Facility Study

BetaActiveHydroTVALBNL

11 MW generation in Marion, TN · In queue since August 2017 · Proposed COD January 2021

11 MW

Capacity

1

Components

Hydro

8y 7m

In Queue

Facility Study

IA Status

COD target: 2021

Interconnection Timeline

Total Duration

3y 5m

Schedule

63 months past proposed COD

Facilities Study50%
Queue EntryAug 4, 2017

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2021-01-15

Project Details

State

TN

County

Marion

Region

Southeast

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Point of Interconnection

Raccoon Mountain 161-kV Substation

Data Source

LBNL