60 MW generation in Monroe, MS · In queue since May 2017 · Proposed COD September 2021
60 MW
Capacity
1
Components
Solar
8y 10m
In Queue
IA Executed
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
4y 4m
Schedule
55 months past proposed COD
Construction75%
Queue EntryMay 23, 2017
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2021-09-15
Project Details
State
MS
County
Monroe
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
Stateline - West Point 161-kV TL
Data Source
LBNL