14 MW generation in Shelby, TN · In queue since November 2016 · Proposed COD March 2018
14 MW
Capacity
1
Components
Gas
9y 4m
In Queue
IA Executed
IA Status
COD target: 2018
Interconnection Timeline
Total Duration
1y 4m
Schedule
98 months past proposed COD
Construction75%
Queue EntryNov 21, 2016
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 24–48 months
Commercial Operation
Proposed COD: 2018-03-01
Project Details
State
TN
County
Shelby
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
Allen 161-kV Substation
Data Source
LBNL