67 MW generation in Lake, TN · In queue since July 2016 · Proposed COD March 2020
67 MW
Capacity
1
Components
Solar
9y 8m
In Queue
IA Executed
IA Status
COD target: 2020
Interconnection Timeline
Total Duration
3y 8m
Schedule
74 months past proposed COD
Construction75%
Queue EntryJul 28, 2016
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2020-03-01
Project Details
State
TN
County
Lake
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
Highway 412-New Tiptonville 161-kV TL
Data Source
LBNL