— Project Summary

Queue ID
TVA-292
Capacity
80 MW
Technology
Solar
Status
active
Location
Lake, TN
Region
Southeast
Developer
IA Status
IA Executed

BetaActiveSolarTVALBNL

80 MW generation in Lake, TN · In queue since April 2016 · Proposed COD March 2023

80 MW

Capacity

1

Components

Solar

9y 11m

In Queue

IA Executed

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

6y 11m

Schedule

36 months past proposed COD

Construction75%
Queue EntryApr 19, 2016

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Proposed COD: 2023-03-31

Project Details

State

TN

County

Lake

Region

Southeast

Developer

Utility

Tennessee Valley Authority

Entity

TVA

Point of Interconnection

Highway 412-New Tiptonville 161-kV TL

Data Source

LBNL

No news available for this project.