80 MW generation in Lake, TN · In queue since April 2016 · Proposed COD March 2023
80 MW
Capacity
1
Components
Solar
9y 11m
In Queue
IA Executed
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
6y 11m
Schedule
36 months past proposed COD
Construction75%
Queue EntryApr 19, 2016
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Proposed COD: 2023-03-31
Project Details
State
TN
County
Lake
Region
Southeast
Developer
—
Utility
Tennessee Valley Authority
Entity
TVA
Point of Interconnection
Highway 412-New Tiptonville 161-kV TL
Data Source
LBNL