103 MW generation in Banner, NE · In queue since February 2018
103 MW
Capacity
1
Components
Wind
8y 1m
In Queue
Suspended
IA Status
Signed Nov 2023
Interconnection Timeline
Queue → IA
5y 9m
Total Duration
5y 9m
Suspended38%
Queue EntryFeb 27, 2018
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementNov 1, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 18–36 months
Commercial Operation
Commercial operation date not yet determined
Project Details
State
NE
County
Banner
Region
West
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Point of Interconnection
Round Top Switching Station
Data Source
LBNL