199 MW hybrid in Moffat, CO · In queue since May 2023 · Proposed COD December 2027
199 MW
Capacity
1
Components
Solar
2y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
4y 7m
In Study38%
Queue EntryMay 30, 2023
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-12-01
Project Details
State
CO
County
Moffat
Region
West
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Point of Interconnection
Craig-Meeker 345 kV Line
Data Source
LBNL