BetaActiveSolarTSGTLBNL
250 MW generation in Lincoln, CO · In queue since May 2024 · Proposed COD July 2027
250 MW
Capacity
1
Components
Solar
1y 10m
In Queue
In Progress (unknown study)
IA Status
COD target: 2027
Interconnection Timeline
Total Duration
3y 2m
In Study38%
Queue EntryMay 29, 2024
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2027-07-01
Project Details
State
CO
County
Lincoln
Region
West
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Point of Interconnection
Big Sandy 230kV Substation
Data Source
LBNL
No news available for this project.