— Project Summary

Queue ID
TSGT-GI-TC-2024-19
Capacity
100 MW
Technology
Battery
Status
active
Location
Montrose, CO
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveBatteryTSGTLBNL

100 MW storage in Montrose, CO · In queue since May 2024 · Proposed COD May 2026

100 MW

Capacity

1

Components

Battery

1y 10m

In Queue

In Progress (unknown study)

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

2 years

In Study38%
Queue EntryMay 7, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-05-31

Project Details

State

CO

County

Montrose

Region

West

Developer

Utility

Tri-State Generation and Transmission Association

Entity

TSGT

Point of Interconnection

Montrose 115kV Substation

Data Source

LBNL