— Project Summary

Queue ID
TSGT-GI-TC-2024-16
Capacity
400 MW
Technology
Wind
Status
active
Location
Laramie, WY
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveWindTSGTLBNL

400 MW generation in Laramie, WY · In queue since May 2023 · Proposed COD December 2027

400 MW

Capacity

1

Components

Wind

2y 10m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

4y 7m

In Study38%
Queue EntryMay 16, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

Project Details

State

WY

County

Laramie

Region

West

Developer

Utility

Tri-State Generation and Transmission Association

Entity

TSGT

Point of Interconnection

Ault-Laramie River Station 345kV Line

Data Source

LBNL

No news available for this project.