— Project Summary

Queue ID
TSGT-GI-TC-2024-14
Capacity
206.01 MW
Technology
Solar
Status
active
Location
Weld, CO
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarTSGTLBNL

206.01 MW generation in Weld, CO · In queue since May 2023 · Proposed COD December 2028

206.01 MW

Capacity

1

Components

Solar

2y 10m

In Queue

In Progress (unknown study)

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5y 7m

In Study38%
Queue EntryMay 31, 2023

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-31

Project Details

State

CO

County

Weld

Region

West

Developer

Utility

Tri-State Generation and Transmission Association

Entity

TSGT

Point of Interconnection

Greenhouse 230kv Substation

Data Source

LBNL

No news available for this project.