— Project Summary

Queue ID
TSGT-GI-TC-2024-13
Capacity
250 MW
Technology
Solar+Battery
Status
active
Location
Routt, CO
Region
West
Developer
IA Status
In Progress (unknown study)

BetaActiveSolarBatteryTSGTLBNL

250 MW hybrid in Routt, CO · In queue since May 2024 · Proposed COD December 2027

250 MW

Capacity

1

Components

Solar

1y 10m

In Queue

In Progress (unknown study)

IA Status

COD target: 2027

Interconnection Timeline

Total Duration

3y 7m

In Study38%
Queue EntryMay 23, 2024

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2027-12-31

Project Details

State

CO

County

Routt

Region

West

Developer

Utility

Tri-State Generation and Transmission Association

Entity

TSGT

Point of Interconnection

Craig-Hayden West 230kV Line

Data Source

LBNL

No news available for this project.