— Project Summary

Queue ID
TSGT-GI-TC-2021-05
Capacity
200 MW
Technology
Solar
Status
active
Location
Mckinley, NM
Region
West
Developer
IA Status
IA Executed

BetaActiveSolarTSGTLBNL

200 MW generation in Mckinley, NM · In queue since March 2021

200 MW

Capacity

1

Components

Solar

5 years

In Queue

IA Executed

IA Status

Signed Nov 2023

Interconnection Timeline

Queue → IA

2y 8m

Total Duration

2y 8m

Construction75%
Queue EntryMar 15, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection AgreementNov 1, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Commercial operation date not yet determined

Project Details

State

NM

County

Mckinley

Region

West

Developer

Utility

Tri-State Generation and Transmission Association

Entity

TSGT

Point of Interconnection

PEGS 230kV Station

Data Source

LBNL

No news available for this project.