40 MW generation in Las Animas, CO · In queue since March 2021
40 MW
Capacity
1
Components
Solar
5 years
In Queue
IA Executed
IA Status
Signed Sep 2024
Interconnection Timeline
Queue → IA
3y 6m
Total Duration
3y 6m
Construction75%
Queue EntryMar 15, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementSep 1, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Commercial operation date not yet determined
Project Details
State
CO
County
Las Animas
Region
West
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Point of Interconnection
Walsenburg-Gladstone 230 kV Line
Data Source
LBNL
No news available for this project.