— Project Summary

Queue ID
TSGT-GI-TC-2021-01
Capacity
145 MW
Technology
Solar
Status
active
Location
Moffat, CO
Region
West
Developer
IA Status
IA Executed

BetaActiveSolarTSGTLBNL

145 MW generation in Moffat, CO · In queue since March 2021

145 MW

Capacity

1

Components

Solar

5 years

In Queue

IA Executed

IA Status

Signed Jun 2024

Interconnection Timeline

Queue → IA

3y 3m

Total Duration

3y 3m

Construction75%
Queue EntryMar 15, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection AgreementJun 30, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Commercial operation date not yet determined

Project Details

State

CO

County

Moffat

Region

West

Developer

Utility

Tri-State Generation and Transmission Association

Entity

TSGT

Point of Interconnection

Craig-Meeker 345kV Line

Data Source

LBNL

No news available for this project.