— Project Summary

Queue ID
TSGT-GI-DISIS-2022-49
Capacity
225 MW
Technology
Solar+Battery
Status
active
Location
Prowers, CO
Region
West
Developer
IA Status
IA Executed

BetaActiveSolarBatteryTSGTLBNL

225 MW hybrid in Prowers, CO · In queue since May 2022

225 MW

Capacity

2

Components

Solar + Battery

3y 10m

In Queue

IA Executed

IA Status

Interconnection Timeline

Total Duration

3y 10m

Construction75%
Queue EntryMay 31, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 18–30 months

Commercial Operation

Commercial operation date not yet determined

Technology
Solar150 MW · 67%
Battery75 MW · 33%
Project Details

State

CO

County

Prowers

Region

West

Developer

Utility

Tri-State Generation and Transmission Association

Entity

TSGT

Point of Interconnection

Lamar 230kV Substation

Data Source

LBNL