— Project Summary

Queue ID
TSGT-GI-DISIS-2022-45
Capacity
199 MW
Technology
Solar+Battery
Status
active
Location
Pueblo, CO
Region
West
Developer
IA Status
System Impact Study

BetaActiveSolarBatteryTSGTLBNL

199 MW hybrid in Pueblo, CO · In queue since May 2022 · Proposed COD December 2026

199 MW

Capacity

1

Components

Solar

3y 10m

In Queue

System Impact Study

IA Status

COD target: 2026

Interconnection Timeline

Total Duration

4y 7m

Impact Study25%
Queue EntryMay 31, 2022

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2026-12-01

Project Details

State

CO

County

Pueblo

Region

West

Developer

Utility

Tri-State Generation and Transmission Association

Entity

TSGT

Point of Interconnection

Huckleberry 230kV Substation

Data Source

LBNL