BetaSuspendedSolarBatteryTSGTLBNL
299 MW hybrid in Kit Carson, CO · In queue since May 2022
299 MW
Capacity
2
Components
Solar + Battery
3y 10m
In Queue
Suspended
IA Status
Interconnection Timeline
Total Duration
3y 10m
Suspended38%
Queue EntryMay 31, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Technology
Solar199 MW · 67%
Battery100 MW · 33%
Project Details
State
CO
County
Kit Carson
Region
West
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Point of Interconnection
Burlington - Lamar 230kV Line
Data Source
LBNL
No news available for this project.