BetaActiveWindTSGTLBNL
199 MW generation in Kiowa, CO · In queue since May 2022
199 MW
Capacity
1
Components
Wind
3y 10m
In Queue
IA Executed
IA Status
Interconnection Timeline
Total Duration
3y 10m
Construction75%
Queue EntryMay 27, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 18–36 months
Commercial Operation
Commercial operation date not yet determined
Project Details
State
CO
County
Kiowa
Region
West
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Point of Interconnection
Lamar-Burlington 230kV Line
Data Source
LBNL
No news available for this project.