398 MW hybrid in Prowers, CO · In queue since May 2022
398 MW
Capacity
2
Components
Solar + Battery
3y 10m
In Queue
Suspended
IA Status
Interconnection Timeline
Total Duration
3y 10m
Suspended38%
Queue EntryMay 27, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Technology
Solar199 MW · 50%
Battery199 MW · 50%
Project Details
State
CO
County
Prowers
Region
West
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Point of Interconnection
Lamar 230kV Substation
Data Source
LBNL