BetaSuspendedSolarBatteryTSGTLBNL
300 MW hybrid in Las Animas, CO · In queue since May 2021
300 MW
Capacity
2
Components
Solar + Battery
4y 10m
In Queue
Suspended
IA Status
Interconnection Timeline
Total Duration
4y 10m
Suspended38%
Queue EntryMay 28, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Commercial operation date not yet determined
Technology
Solar200 MW · 67%
Battery100 MW · 33%
Project Details
State
CO
County
Las Animas
Region
West
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Point of Interconnection
Walsenburg-Gladstone 230kV Line
Data Source
LBNL
No news available for this project.