BetaSuspendedSolarBatteryTSGTLBNL
398 MW hybrid in Converse, WY · In queue since May 2021
398 MW
Capacity
2
Components
Solar + Battery
4y 10m
In Queue
Suspended
IA Status
Signed Jun 2023
Interconnection Timeline
Queue → IA
2y 1m
Total Duration
2y 1m
Suspended38%
Queue EntryMay 28, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementJun 1, 2023
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 18–30 months
Commercial Operation
Commercial operation date not yet determined
Technology
Solar199 MW · 50%
Battery199 MW · 50%
Project Details
State
WY
County
Converse
Region
West
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Point of Interconnection
DJ-LRS 230kV Line
Data Source
LBNL
No news available for this project.