— Project Summary

Queue ID
TSGT-GI-DISIS-2021-10
Capacity
398 MW
Technology
Solar+Battery
Status
suspended
Location
Converse, WY
Region
West
Developer
IA Status
Suspended

BetaSuspendedSolarBatteryTSGTLBNL

398 MW hybrid in Converse, WY · In queue since May 2021

398 MW

Capacity

2

Components

Solar + Battery

4y 10m

In Queue

Suspended

IA Status

Signed Jun 2023

Interconnection Timeline

Queue → IA

2y 1m

Total Duration

2y 1m

Suspended38%
Queue EntryMay 28, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection AgreementJun 1, 2023

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

Construction

Construction pending

Typical: 18–30 months

Commercial Operation

Commercial operation date not yet determined

Technology
Solar199 MW · 50%
Battery199 MW · 50%
Project Details

State

WY

County

Converse

Region

West

Developer

Utility

Tri-State Generation and Transmission Association

Entity

TSGT

Point of Interconnection

DJ-LRS 230kV Line

Data Source

LBNL

No news available for this project.