— Project Summary

Queue ID
TSGT-GI-DISIS-2021-06
Capacity
140 MW
Technology
Solar
Status
active
Location
Montezuma, CO
Region
West
Developer
IA Status
IA Executed

BetaActiveSolarTSGTLBNL

140 MW generation in Montezuma, CO · In queue since May 2021

140 MW

Capacity

1

Components

Solar

4y 10m

In Queue

IA Executed

IA Status

Interconnection Timeline

Total Duration

4y 10m

Construction75%
Queue EntryMay 27, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Commercial operation date not yet determined

Project Details

State

CO

County

Montezuma

Region

West

Developer

Utility

Tri-State Generation and Transmission Association

Entity

TSGT

Point of Interconnection

Main Switch 115kV Substation

Data Source

LBNL