— Project Summary

Queue ID
TSGT-GI-DISIS-2021-04
Capacity
150 MW
Technology
Solar+Battery
Status
suspended
Location
Otero, NM
Region
West
Developer
IA Status
Suspended

BetaSuspendedSolarBatteryTSGTLBNL

150 MW hybrid in Otero, NM · In queue since May 2021

150 MW

Capacity

2

Components

Solar + Battery

4y 10m

In Queue

Suspended

IA Status

Signed Jun 2024

Interconnection Timeline

Queue → IA

3y 1m

Total Duration

3y 1m

Suspended38%
Queue EntryMay 26, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection AgreementJun 28, 2024

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

Construction

Construction pending

Typical: 18–30 months

Commercial Operation

Commercial operation date not yet determined

Technology
Solar100 MW · 67%
Battery50 MW · 33%
Project Details

State

NM

County

Otero

Region

West

Developer

Utility

Tri-State Generation and Transmission Association

Entity

TSGT

Point of Interconnection

Alamogordo-Dona Ana 115kV Line

Data Source

LBNL