BetaSuspendedSolarBatteryTSGTLBNL
150 MW hybrid in Otero, NM · In queue since May 2021
150 MW
Capacity
2
Components
Solar + Battery
4y 10m
In Queue
Suspended
IA Status
Signed Jun 2024
Interconnection Timeline
Queue → IA
3y 1m
Total Duration
3y 1m
Suspended38%
Queue EntryMay 26, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection AgreementJun 28, 2024
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
Construction
Construction pending
Typical: 18–30 months
Commercial Operation
Commercial operation date not yet determined
Technology
Solar100 MW · 67%
Battery50 MW · 33%
Project Details
State
NM
County
Otero
Region
West
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Point of Interconnection
Alamogordo-Dona Ana 115kV Line
Data Source
LBNL
No news available for this project.