BetaActiveSolarTSGTLBNL
120 MW generation in Harding, NM · In queue since April 2021
120 MW
Capacity
1
Components
Solar
4y 11m
In Queue
IA Executed
IA Status
Interconnection Timeline
Total Duration
4y 11m
Construction75%
Queue EntryApr 15, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement executed — binding commitment to build
Typical: 30–60 days (negotiation)
ConstructionCurrent
Project under construction
Typical: 12–24 months
Commercial Operation
Commercial operation date not yet determined
Project Details
State
NM
County
Harding
Region
West
Developer
—
Utility
Tri-State Generation and Transmission Association
Entity
TSGT
Point of Interconnection
Gladstone-Bravo Dome West 115kV Line
Data Source
LBNL
No news available for this project.