— Project Summary

Queue ID
TSGT-GI-DISIS-2021-01
Capacity
120 MW
Technology
Solar
Status
active
Location
Harding, NM
Region
West
Developer
IA Status
IA Executed

BetaActiveSolarTSGTLBNL

120 MW generation in Harding, NM · In queue since April 2021

120 MW

Capacity

1

Components

Solar

4y 11m

In Queue

IA Executed

IA Status

Interconnection Timeline

Total Duration

4y 11m

Construction75%
Queue EntryApr 15, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement executed — binding commitment to build

Typical: 30–60 days (negotiation)

ConstructionCurrent

Project under construction

Typical: 12–24 months

Commercial Operation

Commercial operation date not yet determined

Project Details

State

NM

County

Harding

Region

West

Developer

Utility

Tri-State Generation and Transmission Association

Entity

TSGT

Point of Interconnection

Gladstone-Bravo Dome West 115kV Line

Data Source

LBNL

No news available for this project.