— Project Summary

Queue ID
TEP-95
Capacity
250 MW
Technology
Other
Status
active
Location
Apache, AZ
Region
West
Developer
IA Status

BetaActiveOtherTEPLBNL

250 MW generation in Apache, AZ · In queue since June 2021 · Proposed COD December 2024

250 MW

Capacity

1

Components

Other

4y 9m

In Queue

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 6m

Schedule

15 months past proposed COD

Pre-Study0%
Queue EntryJun 17, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-31

Project Details

State

AZ

County

Apache

Region

West

Developer

Utility

Tucson Electric Power Company

Entity

TEP

Point of Interconnection

Coronado 345kV Substation

Data Source

LBNL

No news available for this project.