BetaActiveOtherTEPLBNL
400 MW generation in Apache, AZ · In queue since April 2021 · Proposed COD December 2021
400 MW
Capacity
1
Components
Other
4y 11m
In Queue
IA Pending
IA Status
COD target: 2021
Interconnection Timeline
Total Duration
8 months
Schedule
52 months past proposed COD
In Study38%
Queue EntryApr 26, 2021
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2021-12-31
Project Details
State
AZ
County
Apache
Region
West
Developer
—
Utility
Tucson Electric Power Company
Entity
TEP
Point of Interconnection
Springerville-Mckinley 345kV Transmission Line
Data Source
LBNL
No news available for this project.