— Project Summary

Queue ID
TEP-86
Capacity
250 MW
Technology
Other
Status
active
Location
Apache, AZ
Region
West
Developer
IA Status
IA Pending

BetaActiveOtherTEPLBNL

250 MW generation in Apache, AZ · In queue since December 2020 · Proposed COD December 2023

250 MW

Capacity

1

Components

Other

5y 3m

In Queue

IA Pending

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

3 years

Schedule

28 months past proposed COD

In Study38%
Queue EntryDec 16, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-12-01

Project Details

State

AZ

County

Apache

Region

West

Developer

Utility

Tucson Electric Power Company

Entity

TEP

Point of Interconnection

Springerville 345kV Substation

Data Source

LBNL

No news available for this project.