— Project Summary

Queue ID
TEP-84
Capacity
500 MW
Technology
Solar+Battery
Status
active
Location
Pima, AZ
Region
West
Developer
IA Status
IA Pending

BetaActiveSolarBatteryTEPLBNL

500 MW hybrid in Pima, AZ · In queue since September 2020 · Proposed COD December 2023

500 MW

Capacity

1

Components

Solar

5y 6m

In Queue

IA Pending

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

3y 3m

Schedule

27 months past proposed COD

In Study38%
Queue EntrySep 30, 2020

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-12-31

Project Details

State

AZ

County

Pima

Region

West

Developer

Utility

Tucson Electric Power Company

Entity

TEP

Point of Interconnection

Pinal West - South Loop 345kV

Data Source

LBNL

No news available for this project.