300 MW generation in Apache, AZ · In queue since February 2020 · Proposed COD October 2023
300 MW
Capacity
1
Components
Other
6y 1m
In Queue
IA Pending
IA Status
COD target: 2023
Interconnection Timeline
Total Duration
3y 8m
Schedule
30 months past proposed COD
In Study38%
Queue EntryFeb 27, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2023-10-01
Project Details
State
AZ
County
Apache
Region
West
Developer
—
Utility
Tucson Electric Power Company
Entity
TEP
Point of Interconnection
Springerville 345kV Substation
Data Source
LBNL
No news available for this project.