BetaActiveOtherTEPLBNL
80 MW generation in Pima, AZ · In queue since January 2020 · Proposed COD November 2022
80 MW
Capacity
1
Components
Other
6y 2m
In Queue
IA Pending
IA Status
COD target: 2022
Interconnection Timeline
Total Duration
2y 10m
Schedule
41 months past proposed COD
In Study38%
Queue EntryJan 24, 2020
Interconnection request submitted to ISO/RTO
Interconnection StudyCurrent
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2022-11-20
Project Details
State
AZ
County
Pima
Region
West
Developer
—
Utility
Tucson Electric Power Company
Entity
TEP
Point of Interconnection
Tortolita 138kV
Data Source
LBNL