— Project Summary

Queue ID
TEP-62
Capacity
300 MW
Technology
Other
Status
active
Location
Pima, AZ
Region
West
Developer
IA Status
IA Pending

BetaActiveOtherTEPLBNL

300 MW generation in Pima, AZ · In queue since September 2018 · Proposed COD May 2023

300 MW

Capacity

1

Components

Other

7y 6m

In Queue

IA Pending

IA Status

COD target: 2023

Interconnection Timeline

Total Duration

4y 8m

Schedule

35 months past proposed COD

In Study38%
Queue EntrySep 27, 2018

Interconnection request submitted to ISO/RTO

Interconnection StudyCurrent

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2023-05-01

Project Details

State

AZ

County

Pima

Region

West

Developer

Utility

Tucson Electric Power Company

Entity

TEP

Point of Interconnection

Pinal West 345 kV

Data Source

LBNL

No news available for this project.