— Project Summary

Queue ID
TEP-165
Capacity
100 MW
Technology
Solar+Battery
Status
active
Location
Pima, AZ
Region
West
Developer
IA Status

BetaActiveSolarBatteryTEPLBNL

100 MW hybrid in Pima, AZ · In queue since September 2023 · Proposed COD December 2028

100 MW

Capacity

1

Components

Solar

2y 6m

In Queue

IA Status

COD target: 2028

Interconnection Timeline

Total Duration

5y 3m

Pre-Study0%
Queue EntrySep 29, 2023

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2028-12-01

Project Details

State

AZ

County

Pima

Region

West

Developer

Utility

Tucson Electric Power Company

Entity

TEP

Point of Interconnection

Sonoran 138kV Substation

Data Source

LBNL

No news available for this project.