BetaActiveBatteryTEPLBNL
150 MW storage in Pima, AZ · In queue since December 2022 · Proposed COD December 2026
150 MW
Capacity
1
Components
Battery
3y 3m
In Queue
—
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4 years
Pre-Study0%
Queue EntryDec 19, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-01
Project Details
State
AZ
County
Pima
Region
West
Developer
—
Utility
Tucson Electric Power Company
Entity
TEP
Point of Interconnection
Kino 138kV Substation
Data Source
LBNL