— Project Summary

Queue ID
TEP-132
Capacity
150 MW
Technology
Battery
Status
active
Location
Pima, AZ
Region
West
Developer
IA Status

BetaActiveBatteryTEPLBNL

150 MW storage in Pima, AZ · In queue since July 2022 · Proposed COD June 2025

150 MW

Capacity

1

Components

Battery

3y 8m

In Queue

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

2y 11m

Schedule

10 months past proposed COD

Pre-Study0%
Queue EntryJul 14, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-06-02

Project Details

State

AZ

County

Pima

Region

West

Developer

Utility

Tucson Electric Power Company

Entity

TEP

Point of Interconnection

Robert Bills-Wilmot 138kV Transmission Line

Data Source

LBNL

No news available for this project.