BetaActiveBatteryTEPLBNL
150 MW storage in Pima, AZ · In queue since July 2022 · Proposed COD June 2025
150 MW
Capacity
1
Components
Battery
3y 8m
In Queue
—
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
2y 11m
Schedule
10 months past proposed COD
Pre-Study0%
Queue EntryJul 14, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-06-02
Project Details
State
AZ
County
Pima
Region
West
Developer
—
Utility
Tucson Electric Power Company
Entity
TEP
Point of Interconnection
Robert Bills-Wilmot 138kV Transmission Line
Data Source
LBNL
No news available for this project.