— Project Summary

Queue ID
TEP-125
Capacity
1000 MW
Technology
Solar+Battery
Status
active
Location
Apache, AZ
Region
West
Developer
IA Status

BetaActiveSolarBatteryTEPLBNL

1,000 MW hybrid in Apache, AZ · In queue since June 2022 · Proposed COD December 2025

1,000 MW

Capacity

1

Components

Solar

3y 9m

In Queue

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 6m

Schedule

3 months past proposed COD

Pre-Study0%
Queue EntryJun 28, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

Project Details

State

AZ

County

Apache

Region

West

Developer

Utility

Tucson Electric Power Company

Entity

TEP

Point of Interconnection

Springerville 345kV Substation

Data Source

LBNL

No news available for this project.