150 MW storage in Pinal, AZ · In queue since May 2022 · Proposed COD December 2026
150 MW
Capacity
1
Components
Battery
3y 10m
In Queue
—
IA Status
COD target: 2026
Interconnection Timeline
Total Duration
4y 7m
Pre-Study0%
Queue EntryMay 20, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2026-12-01
Project Details
State
AZ
County
Pinal
Region
West
Developer
—
Utility
Tucson Electric Power Company
Entity
TEP
Point of Interconnection
Pinal West 345kV Substation
Data Source
LBNL