BetaActiveWindTEPLBNL
200 MW generation in Cochise, AZ · In queue since May 2022 · Proposed COD December 2025
200 MW
Capacity
1
Components
Wind
3y 10m
In Queue
—
IA Status
COD target: 2025
Interconnection Timeline
Total Duration
3y 7m
Schedule
3 months past proposed COD
Pre-Study0%
Queue EntryMay 2, 2022
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2025-12-31
Project Details
State
AZ
County
Cochise
Region
West
Developer
—
Utility
Tucson Electric Power Company
Entity
TEP
Point of Interconnection
Sprinerville-Vail 345kV Transmission Line
Data Source
LBNL