— Project Summary

Queue ID
TEP-120
Capacity
200 MW
Technology
Wind
Status
active
Location
Cochise, AZ
Region
West
Developer
IA Status

BetaActiveWindTEPLBNL

200 MW generation in Cochise, AZ · In queue since May 2022 · Proposed COD December 2025

200 MW

Capacity

1

Components

Wind

3y 10m

In Queue

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 7m

Schedule

3 months past proposed COD

Pre-Study0%
Queue EntryMay 2, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-31

Project Details

State

AZ

County

Cochise

Region

West

Developer

Utility

Tucson Electric Power Company

Entity

TEP

Point of Interconnection

Sprinerville-Vail 345kV Transmission Line

Data Source

LBNL

No news available for this project.