— Project Summary

Queue ID
TEP-118
Capacity
300 MW
Technology
Wind
Status
active
Location
Apache, AZ
Region
West
Developer
IA Status

BetaActiveWindTEPLBNL

300 MW generation in Apache, AZ · In queue since April 2022 · Proposed COD December 2025

300 MW

Capacity

1

Components

Wind

3y 11m

In Queue

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 8m

Schedule

4 months past proposed COD

Pre-Study0%
Queue EntryApr 4, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-01

Project Details

State

AZ

County

Apache

Region

West

Developer

Utility

Tucson Electric Power Company

Entity

TEP

Point of Interconnection

Springerville 345kV Substation

Data Source

LBNL

No news available for this project.