— Project Summary

Queue ID
TEP-116
Capacity
100 MW
Technology
Other
Status
active
Location
Pima, AZ
Region
West
Developer
IA Status

BetaActiveOtherTEPLBNL

100 MW generation in Pima, AZ · In queue since March 2022 · Proposed COD December 2025

100 MW

Capacity

1

Components

Other

4 years

In Queue

IA Status

COD target: 2025

Interconnection Timeline

Total Duration

3y 9m

Schedule

4 months past proposed COD

Pre-Study0%
Queue EntryMar 29, 2022

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2025-12-01

Project Details

State

AZ

County

Pima

Region

West

Developer

Utility

Tucson Electric Power Company

Entity

TEP

Point of Interconnection

Cisne 138kV

Data Source

LBNL