— Project Summary

Queue ID
TEP-109
Capacity
200 MW
Technology
Other
Status
active
Location
Pima, AZ
Region
West
Developer
TEP
IA Status

BetaActiveOtherTEPLBNL

200 MW generation in Pima, AZ · In queue since December 2021 · Proposed COD May 2024

200 MW

Capacity

1

Components

Other

4y 3m

In Queue

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

2y 5m

Schedule

22 months past proposed COD

Pre-Study0%
Queue EntryDec 21, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-05-31

Project Details

State

AZ

County

Pima

Region

West

Developer

TEP

Utility

Tucson Electric Power Company

Entity

TEP

Point of Interconnection

Vail 138kV Substation

Data Source

LBNL

No news available for this project.