— Project Summary

Queue ID
TEP-107
Capacity
400 MW
Technology
Other
Status
active
Location
Pima, AZ
Region
West
Developer
IA Status

BetaActiveOtherTEPLBNL

400 MW generation in Pima, AZ · In queue since December 2021 · Proposed COD December 2024

400 MW

Capacity

1

Components

Other

4y 3m

In Queue

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3 years

Schedule

15 months past proposed COD

Pre-Study0%
Queue EntryDec 8, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-31

Project Details

State

AZ

County

Pima

Region

West

Developer

Utility

Tucson Electric Power Company

Entity

TEP

Point of Interconnection

Tortolita 138kV

Data Source

LBNL

No news available for this project.