BetaActiveOtherTEPLBNL
320 MW generation in Pima, AZ · In queue since December 2021 · Proposed COD December 2024
320 MW
Capacity
1
Components
Other
4y 3m
In Queue
—
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3 years
Schedule
15 months past proposed COD
Pre-Study0%
Queue EntryDec 8, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-31
Project Details
State
AZ
County
Pima
Region
West
Developer
—
Utility
Tucson Electric Power Company
Entity
TEP
Point of Interconnection
North Loop 138kV Substation
Data Source
LBNL