BetaActiveOtherTEPLBNL
768 MW generation in Apache, AZ · In queue since November 2021 · Proposed COD December 2024
768 MW
Capacity
1
Components
Other
4y 4m
In Queue
—
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
3y 1m
Schedule
15 months past proposed COD
Pre-Study0%
Queue EntryNov 9, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-12-31
Project Details
State
AZ
County
Apache
Region
West
Developer
—
Utility
Tucson Electric Power Company
Entity
TEP
Point of Interconnection
Springerville 345kV Substation
Data Source
LBNL