— Project Summary

Queue ID
TEP-103
Capacity
768 MW
Technology
Other
Status
active
Location
Apache, AZ
Region
West
Developer
IA Status

BetaActiveOtherTEPLBNL

768 MW generation in Apache, AZ · In queue since November 2021 · Proposed COD December 2024

768 MW

Capacity

1

Components

Other

4y 4m

In Queue

IA Status

COD target: 2024

Interconnection Timeline

Total Duration

3y 1m

Schedule

15 months past proposed COD

Pre-Study0%
Queue EntryNov 9, 2021

Interconnection request submitted to ISO/RTO

Interconnection Study

Project undergoes interconnection studies to assess grid impact.

Typical: 18–36 months

Interconnection Agreement

Interconnection agreement not yet executed

Typical: 30–60 days (negotiation)

Commercial Operation

Proposed COD: 2024-12-31

Project Details

State

AZ

County

Apache

Region

West

Developer

Utility

Tucson Electric Power Company

Entity

TEP

Point of Interconnection

Springerville 345kV Substation

Data Source

LBNL