BetaActiveOtherTEPLBNL
250 MW generation in Pima, AZ · In queue since October 2021 · Proposed COD May 2024
250 MW
Capacity
1
Components
Other
4y 5m
In Queue
—
IA Status
COD target: 2024
Interconnection Timeline
Total Duration
2y 7m
Schedule
23 months past proposed COD
Pre-Study0%
Queue EntryOct 30, 2021
Interconnection request submitted to ISO/RTO
Interconnection Study
Project undergoes interconnection studies to assess grid impact.
Typical: 18–36 months
Interconnection Agreement
Interconnection agreement not yet executed
Typical: 30–60 days (negotiation)
Commercial Operation
Proposed COD: 2024-05-01
Project Details
State
AZ
County
Pima
Region
West
Developer
—
Utility
Tucson Electric Power Company
Entity
TEP
Point of Interconnection
North Loop 138kV Substation
Data Source
LBNL